Contact us About us Media far fa-map-marker-alt Find a Branch far fa-phone-alt 13 15 52 far fa-user-alt Coates Connect far fa-shopping-cart Hire Now

Equipment for Hire

Access Earthmoving Lighting Site Accommodation Air & Air Accessories Floor & Cleaning Materials Handling Tools & Equipment Concrete & Masonry Generators & Power Distribution Pipeline Testing Traffic Management Confined Space Entry Ladders & Scaffolding Propping & Structural Support Trucks Vehicles & Trailers Compaction Landscaping Pumps & Fluid Management Welding Construction Lasers Lift & Shift Shoring View All Equipment

Engineering Solutions

Design & Installation Water Management Traffic Management View all Engineering Solutions      

Industrial Solutions

Project Planning Equipment Solutions Systems & Experience View all Industrial Solutions      

Training Courses

Asbestos Removal Electrical Safety Laser Safety Underground Assets Confined Space Elevated Work Platforms Load restraint & plant safety VOC Construction and Small Equipment Forklift Traffic Control Work at Heights       View all Training Courses

Technology

Iot and Smart Job Sites Coates Connect SiteIQ Drones and digital twins Product technology View all Technology

19 NOVEMBER 2019

IN THE TANK

LATEST FROM US

Adelaide Airport has been undergoing upgrades in the past two years to meet increasing aviation activity which saw a 50 per cent increase in passenger numbers between 2005 and 2018.

The upgrades include lengthening the runway and increasing the capacity of the terminals and associated infrastructure. It has also upgraded its emergency systems, including the power back-up for the airport.

The new generators require their own underground tanks, holding 55,000 litres of diesel, enough to power the airport operations through a high-voltage connection for at least three days without grid power. The diesel storage also needs a pumping system.

The electrical contractors needed to excavate a pit that was 3.5 metres deep, 17 metres long and 5.5 metres wide. Supporting works had to be constructed in the pit, so it had to be supported and dewatered for the duration of the construction.

Coates Hire’s Engineering and Technical team was mobilised for the job which had to be carried out to strict standards because of its role in civil aviation and its status as critical infrastructure.

Scott Stanley, Product Specialist - Pumps, Traffic, Shoring & Lift & Shift, says the Coates Hire team was engaged early.

“We’re experts in shoring and propping and the client needed a full scope of service on this project,” says Stanley. “We assisted the client in gathering geotechnical reports, we assessed the requirements and designed the solution with our engineers.”

Stanley says once the design had been accepted by the client’s engineering company, Coates Hire then supplied and installed the propping solution, which included modular components that were fabricated and “run-up” – or put together in a dry run – at the Coates Hire branch. Coates Hire also project-managed the excavation process.

The propping solution included a sheet-pile perimeter wall, held up with 11 hydraulic rams. To keep the pit dry, the team installed a well-point dewatering system, powered by pumps that drew water from the site at 30 litres per second, which was filtered and treated.

“The client was eager to team up with Coates Hire,” says Stanley. “Our experience was the main selling point, ensuring we educated the customer on the risks involved and how we could be adaptive to solve any unforeseen issues during install.”

Stanley says Coates Hire engineers are experienced in modelling excavation sites and mitigating risk.
“We collect and review information so clients can see what actually happens in projects similar to theirs,” says Stanley. “Seeing what can go wrong is as important as knowing the successful outcome.”

Along with the propping and dewatering, Coates Hire provided equipment and operators to complete the pre-auguring, bulk-out, spoil-removal, base-preparation, backfill and earth works. Coates Hire even consulted on the handling of asbestos pipes found in the ground during excavations.

Stanley says the Coates Hire team is expert at creating safe and environmentally responsible excavations, with the experience to adapt to any challenges that arise.

“Once you start digging, challenges always emerge. We can prepare the client and ensure they’re ready to adapt.”
 
If you require more information or would like to contact our Coates Hires Specialty Team click here.

SHARE THIS ARTICLE

{{ socialIcon(api.type) }} {{ socialIcon(api.type) }} {{ socialIcon(api.type) }}
Find out how we can help with your project fas fa-phone-alt CALL US 13 15 52 Submit Enquiry

By submitting this enquiry you agree to Coates's Communications Terms & Conditions

Give us a call
fas fa-phone-alt 13 15 52 fas fa-check 24/7 Online Services fas fa-check Safety Standard Guarantee fas fa-check Same day delivery available
far fa-times-circle Your enquiry has been submitted

Thank you for your enquiry. One of our team members will get back to you as soon as possible.